Trending Now

Federal Court of Australia makes first aggregate damages award in a funded representative proceeding in Toyota Class Action

The following piece was contributed by Martin del Gallego and Matthew Harris of Australian law firm, Piper Alderman.

This article considers a recent decision of the Federal Court of Australia, awarding damages to class action claimants on an aggregate basis.  Aggregate damages is a rare global award which covers all group members described or identified in the award.  This was the first instance of aggregate damages being awarded to a funded litigant in Australia, and may spur a trend in representative claims brought on this basis.

In Williams v Toyota Motor Corporation Australia Limited (Initial Trial) [2022] FCA 344, Justice Michael Lee relied on s 33Z(1)(e) of the Federal Court of Australia Act 1976 (Cth) (the Act) to award damages to group members in possession of certain Toyota vehicles throughout the entirety of the claim period, calculated as the percentage reduction in value of their vehicle or vehicles.  It has been estimated that Toyota’s total aggregate damages bill may exceed AU$2 billion.

Key Takeaways

  • For an order of aggregate damages to be made in a representative proceeding, the Court needs to be satisfied on a principled basis with which to assess and distribute the relief;
  • The analysis must be informed by general principles governing the assessment of damages, and can result in an award of aggregated damages applying to a specific class of group members within a representative proceeding;
  • While the judgment is liable to spur a trend in claims for aggregate damages, precisely how such an award will impact the approval of legal costs and a funder’s commission remains to be seen.

Background to the proceedings

The case before the Court concerned claims relating to Toyota’s supply of 264,170 defective diesel vehicles to Australian consumers between 1 October 2015 and 23 April 2020 (Relevant Period).  These vehicles were fitted with diesel combustion engines and a ‘diesel exhaust after treatment system’, or ‘DPF’, aimed at reducing harmful pollutants and other emissions from the engine.  The case alleged that the vehicles were defective because the DPF was not designed to function during all reasonable driving conditions, and even if driven normally, there was a propensity for the car’s exhaust to emit excessive white smoke and malodour, and cause reduced fuel efficiency and trigger ‘excessive’ notifications prompting the need for service or repair.

In alleging that the vehicles were not of ‘acceptable quality’ in breach of the statutory guarantee under s 54 of the Australian Consumer Law (ACL), and that Toyota’s conduct had been misleading and deceptive in contravention of ss 18, 29(1)(a) and (g), and 33 of the ACL, the lead applicant sought two types of damages under s 272 of the ACL:

  • Under s 272(1)(a), damages for the reduction in value of each relevant vehicle resulting from the failure to comply with s 54 of the ACL; and
  • Under 272(1)(b), other reasonably foreseeable loss or damage incurred as a result of the defect and failure to comply with s 54 of the ACL, including excess taxes, fuel consumption, financing costs, servicing costs and lost income.

Of these heads of damage, only two were suitable for determination at the initial trial of the lead applicant’s claim:  the ‘reduction in value’ damages under s 272(1)(a) and damages for excess GST paid by group members in connection with acquiring the relevant vehicles under s 272(1)(b).  (A separate question had been asked and answered in an earlier interlocutory application in the case, clearing the way for a potential aggregate damages award, in respect of only part of the lead applicant and group members’ claims.[1])

Aggregate Damages

Having found in favour of the lead applicant, on among other things, their ‘acceptable quality’ cases, Justice Lee also found that the same determinations could be made on a common basis for the remainder of group members.  His Honour found that the lead applicant and group members were entitled to damages for the reduction in value of their vehicles, and for excess GST paid in connection with that reduction.  Accordingly, it was necessary for his Honour to determine a principled basis for arriving at a quantum of the reduced value which could be applied on an aggregate basis to all relevant group members.

The Federal Court’s power to award damages on an aggregate basis is found in s 33Z of the Act. This section provides, among other things, that the Court may, in determining a matter in a representative proceeding, make an award of damages for group members, sub‑group members or individual group members, being damages consisting of specified amounts or amounts worked out in such manner as the Court specifies,[2] or award damages in an aggregate amount without specifying amounts awarded in respect of individual group members.[3]  Further, subject to section 33V of the Act, the Court is not to make an award of damages under s 33Z(1)(f) unless a reasonably accurate assessment can be made of the total amount to which group members will be entitled under the judgment.[4]

Noting that class actions were not the ‘Galapagos islands’ of litigation, Justice Lee observed that an award of damages, even on an aggregate basis, was subject to two overarching principles as to the award of compensatory damages.[5]  His Honour observed that an award of compensatory damages must be considered in the light of the overriding compensatory principle, and that even where the process of estimating damages is difficult, the Court ‘must do what it can’, this principle equally applying to an assessment of ‘reduction in value’ damages.

Justice Lee found that the Court is not permitted, by s 33Z of the Act, to take an approach of awarding aggregate damages on a per vehicle basis and determining the separate question of distribution at a later stage. Because of this, his Honour was faced with a challenge of how to distribute relief to group members who had possessed the relevant vehicles for only part of the Relevant Period.  His Honour termed these group members as ‘Partial Period Group Members’ and concluded at [432]:

The bottom line is that without knowing the price at which, or the time at which, the Partial Period Group Members bought and sold Relevant Vehicles on the secondary market, one cannot determine on a principled basis how the compensation for the owners of those Relevant Vehicles ought to be assessed or distributed. One must always bear in mind the whole object of any award of damages is to put the claimant in the position the claimant would have been in but for the contravening conduct.

Ultimately, the Partial Period Group Members will be required to undertake an individualised assessment of their loss. For the ‘Entire Period Group Members’, that is, people who possessed the relevant vehicles throughout the entirety of the Relevant Period, the Court awarded aggregate damages under s 33Z(1)(e) of the Act.  The award of aggregate damages for the Entire Period Group Members was calculated on the basis of a 17.5% reduction in value of the average retail price of the particular type of vehicle at the particular time it was purchased.  In circumstances where the group member paid a price lower than the average retail price for their vehicle, the lower of the two prices was said to be the applicable comparator from which the 17.5% reduction in value is to be calculated.[6]  In being satisfied there was a reduction in value of the relevant vehicles of 17.5% resulting from the failure to comply with s 54 of the ACL, Lee J also found that Entire Period Group Members were also entitled to recover the excess GST they paid on that reduction in value, calculated as 10% of the reduction in value.[7]

Regarding the claim for damages under s 33Z(1)(f) of the Act, the Court declined to award aggregate damages on this basis, because his Honour was not satisfied that a reasonably accurate estimate could be made of the total amount owing to group members as required by s 33Z(3).

Conclusion

Williams is the first instance of a Court awarding aggregate damages in a funded representative proceeding, and provides helpful guidance on how the Court will approach such claims, particularly where only part of the claim is suitable for determination on an aggregate basis.  That said, while Justice Lee found in favour of the class on the issue, it is plain that such an assessment will need to be carried out on a case-by-case basis.

About the Authors

Martin del Gallego, Partner

Martin is Chambers & Partners recognised commercial litigator with 15 years’ experience in high stakes, high value litigation. Martin specialises in class action and funded litigation, with expertise across a broad range of sectors including financial services, energy & resources, construction and insolvency.

Matthew Harris, Lawyer

Matthew is a litigation and dispute resolution lawyer at Piper Alderman with a primary focus on corporate and commercial disputes. Matthew is involved in a number of large, complex matters in jurisdictions across Australia.

For queries or comments in relation to this article please contact Kat Gieras, Litigation Group Project Coordinator | T: +61 7 3220 7765 | E:  kgieras@piperalderman.com.au

[1] Williams v Toyota Motor Corporation Australia Limited [2021] FCA 1425.

[2] Federal Court of Australia Act 1976 (Cth) s 33Z(1)(e).

[3] Ibid s 33Z(1)(f).

[4] Ibid s 33Z(3).

[5] Williams [421]-[423].

[6] Williams [446].

[7] Williams [492].

Case Developments

View All

Montero Agrees to Distribution of US$27 Million Settlement from Tanzania

By Harry Moran |

Montero Mining and Exploration Ltd. (TSX-V: MON) (“Montero” or the “Company”) announces that it has finalised the distribution of the US$27,000,000 settlement with its litigation funders, Omni Bridgeway (Canada). The settlement amount was agreed with the United Republic of Tanzania (“Tanzania”) in the dispute over the expropriation of Montero’s Wigu Hill rare earth element project (“Wigu Hill”).

The settlement amount of US$27,000,000 is payable over three instalments, and is to be distributed as follows:

  • First payment: US$12,000,000 received on November 20, 2024, and distributed between Montero and Omni Bridgeway (Canada), the Company’s litigation funder.
  • Second payment: US$8,000,000 due by January 31, 2025, to be distributed to Montero and to pay all legal fees.
  • Third payment: US$7,000,000 due by February 28, 2025, to be distributed entirely to Montero.

After paying funders and legal costs, the net amount due to Montero will be approximately C$20,577,545 (US$14,458,138).

Dr Tony Harwood, President and CEO of Montero commented: “I am pleased Montero successfully achieved an amicable distribution of proceeds of over C$20,000,000. We wish Tanzania success in attracting new mining investments and look forward to receiving the final two payments due within the next 5 weeks. Further notice of payments received will be forthcoming.

ICSID Arbitration

Montero and Tanzania jointly requested the arbitral tribunal to suspend the ICSID arbitration proceedings after receiving the first payment. Upon receipt of the final payment as scheduled, the parties will formally request the tribunal to discontinue the ICSID arbitration in its entirety.

Distribution of Funds

Montero is considering a return of capital distribution to shareholders. The exact amount is yet to be determined and will be subject to accounting review and board approval. In addition, Montero will retain funds to cover legal, taxation, and administrative expenses, including potential costs for arbitral proceedings, or enforcement actions in the event of delays or non-payment of the second or third instalments. The latter will now be the sole responsibility of Montero. The net amount of the award after deducting payments to the funder and covering legal expenses, cannot be determined with certainty, and no guarantees can be provided. Further announcements will be made in due course.

Disclaimer

The conclusion of the ICSID arbitration and payment of the remaining instalments is conditional on Tanzania’s compliance with the settlement agreement. The agreement does not provide for any security for the benefit of Montero in case Tanzania would not pay any instalment, in which case Montero can either resume the ICSID arbitration or seek enforcement of the settlement agreement.

About Montero

Montero has agreed to a US$27,000,000 settlement amount to end its dispute with the United Republic of Tanzania for the expropriation of the Wigu Hill rare earth element project. The Company is also advancing the Avispa copper-molybdenum project in Chile and is seeking a joint venture partner. Montero’s board of directors and management have an impressive track record of successfully discovering and advancing precious metal and copper projects. Montero trades on the TSX Venture Exchange under the symbol MON and has 50,122,975 shares outstanding.

CAT Finds in Favour of Professor Andreas Stephan in Amazon Claims

By Harry Moran |

Whilst last week saw a flurry of activity in the Competition Appeal Tribunal (CAT) as trials began in multiple collective proceedings, this week has seen the Tribunal hand down a ruling in a carriage dispute between two claims both targeting Amazon for allegations of anticompetitive behaviour.

A press release from Geradin Partners highlights the judgment from the CAT in a carriage dispute, which saw the Tribunal find in favour of Professor Andreas Stephan in collective proceedings being brought against Amazon. The carriage dispute related to the parallel claims brought by Professor Stephan and by the British Independent Retailers Association (BIRA), over allegations that Amazon engaged in anticompetitive practices that harmed third-party sellers on the online marketplace. Professor Stephan’s proceedings had instructed Geradin Partners and secured litigation funding from Innsworth, whilst BIRA had instructed Willkie Farr & Gallagher and agreed to funding from Litigation Capital Management (LCM).

In its ruling, the CAT found that whilst BIRA had an advantage in its suitability to act as the class representative, “this was clearly outweighed by the factors which favour Prof Stephan”, which it identified as “the scope of the claims and the expert methodology.” Although the CAT highlighted that the breadth of Professor Stephan’s claims “would no doubt enlarge the scope of a trial and therefore make it more complicated”, the ruling cited case law in emphasising that his claims “more consistent with the goals of access to justice by capturing more viable claims”.

The published judgment also shed light on the details of the funding arrangements in the claims. Professor Stephan’s litigation funding agreement (LFA) with Innsworth committed a maximum of £32.9 million to cover costs and expenses, with an additional commitment “to pay adverse costs of £5 million until the grant or refusal of a CPO and of £20 million thereafter.” As to the returns outlined in the funding agreement, Professor Stephan’s LFA with Innsworth “provides for a total multiple rising from 4 up to 10 (if the recovery is after the commencement of the substantive trial).” The CAT noted that the returns from Professor Stephan’s LFA were higher than for the funder in the BIRA claim, in the conclusion of its examination the Tribunal noted that “the funding arrangements of the two applications are a neutral factor in choosing between them.”

The CAT’s full judgment in the carriage dispute can be read here.

Additional analysis of the CAT’s ruling and its implications for future carriage disputes for funded proceedings can be found in a LinkedIn post from Matthew Lo, director at Exton Advisors.

Judge Preska Orders Argentina to Comply with Burford Discovery Request

By Harry Moran |

As we enter yet another year in the story of the $16.1 billion award in the case funded by Burford Capital against the YPF oil and gas company, a US judge has ordered the Argentine government to provide additional information about the country’s financial assets to the funder as part of its efforts to collect on the award.

An article in the Buenos Aires Herald provides an update on the ongoing fight to recover the $16.1 billion award in the YPF lawsuit, as a New York judge ordered Argentina to comply with a discovery request for information around the Argentine Central Bank’s gold reserves. The order handed down by Judge Loretta Preska followed the request made by Burford Capital in October of last year, with the litigation funder citing media reports that Argentina’s Central Bank had moved a portion of its gold reserves overseas.

Lawyers for Argentina’s government had submitted a letter last week arguing against the discovery request on the grounds that the Argentine Republic and Central Bank are legally separate entities, and that any such gold reserves have “special protection from execution under [United States’ Foreign Sovereign Immunities Act] and UK law.” Responding to these arguments in her order, Judge Preska stated plainly that “regardless of whether the gold reserves are held by [the Central Bank], the Republic shall produce its own documents concerning the reserves.”

Judge Preska also ordered the Argentine government to provide additional information concerning its SWIFT data on its overseas accounts and for documents from another lawsuit brought against the Republic, saying that all this information could “lead to other executable assets.”

The following piece was contributed by Martin del Gallego and Matthew Harris of Australian law firm, Piper Alderman.

This article considers a recent decision of the Federal Court of Australia, awarding damages to class action claimants on an aggregate basis.  Aggregate damages is a rare global award which covers all group members described or identified in the award.  This was the first instance of aggregate damages being awarded to a funded litigant in Australia, and may spur a trend in representative claims brought on this basis.

In Williams v Toyota Motor Corporation Australia Limited (Initial Trial) [2022] FCA 344, Justice Michael Lee relied on s 33Z(1)(e) of the Federal Court of Australia Act 1976 (Cth) (the Act) to award damages to group members in possession of certain Toyota vehicles throughout the entirety of the claim period, calculated as the percentage reduction in value of their vehicle or vehicles.  It has been estimated that Toyota’s total aggregate damages bill may exceed AU$2 billion.

Key Takeaways

  • For an order of aggregate damages to be made in a representative proceeding, the Court needs to be satisfied on a principled basis with which to assess and distribute the relief;
  • The analysis must be informed by general principles governing the assessment of damages, and can result in an award of aggregated damages applying to a specific class of group members within a representative proceeding;
  • While the judgment is liable to spur a trend in claims for aggregate damages, precisely how such an award will impact the approval of legal costs and a funder’s commission remains to be seen.

Background to the proceedings

The case before the Court concerned claims relating to Toyota’s supply of 264,170 defective diesel vehicles to Australian consumers between 1 October 2015 and 23 April 2020 (Relevant Period).  These vehicles were fitted with diesel combustion engines and a ‘diesel exhaust after treatment system’, or ‘DPF’, aimed at reducing harmful pollutants and other emissions from the engine.  The case alleged that the vehicles were defective because the DPF was not designed to function during all reasonable driving conditions, and even if driven normally, there was a propensity for the car’s exhaust to emit excessive white smoke and malodour, and cause reduced fuel efficiency and trigger ‘excessive’ notifications prompting the need for service or repair.

In alleging that the vehicles were not of ‘acceptable quality’ in breach of the statutory guarantee under s 54 of the Australian Consumer Law (ACL), and that Toyota’s conduct had been misleading and deceptive in contravention of ss 18, 29(1)(a) and (g), and 33 of the ACL, the lead applicant sought two types of damages under s 272 of the ACL:

  • Under s 272(1)(a), damages for the reduction in value of each relevant vehicle resulting from the failure to comply with s 54 of the ACL; and
  • Under 272(1)(b), other reasonably foreseeable loss or damage incurred as a result of the defect and failure to comply with s 54 of the ACL, including excess taxes, fuel consumption, financing costs, servicing costs and lost income.

Of these heads of damage, only two were suitable for determination at the initial trial of the lead applicant’s claim:  the ‘reduction in value’ damages under s 272(1)(a) and damages for excess GST paid by group members in connection with acquiring the relevant vehicles under s 272(1)(b).  (A separate question had been asked and answered in an earlier interlocutory application in the case, clearing the way for a potential aggregate damages award, in respect of only part of the lead applicant and group members’ claims.[1])

Aggregate Damages

Having found in favour of the lead applicant, on among other things, their ‘acceptable quality’ cases, Justice Lee also found that the same determinations could be made on a common basis for the remainder of group members.  His Honour found that the lead applicant and group members were entitled to damages for the reduction in value of their vehicles, and for excess GST paid in connection with that reduction.  Accordingly, it was necessary for his Honour to determine a principled basis for arriving at a quantum of the reduced value which could be applied on an aggregate basis to all relevant group members.

The Federal Court’s power to award damages on an aggregate basis is found in s 33Z of the Act. This section provides, among other things, that the Court may, in determining a matter in a representative proceeding, make an award of damages for group members, sub‑group members or individual group members, being damages consisting of specified amounts or amounts worked out in such manner as the Court specifies,[2] or award damages in an aggregate amount without specifying amounts awarded in respect of individual group members.[3]  Further, subject to section 33V of the Act, the Court is not to make an award of damages under s 33Z(1)(f) unless a reasonably accurate assessment can be made of the total amount to which group members will be entitled under the judgment.[4]

Noting that class actions were not the ‘Galapagos islands’ of litigation, Justice Lee observed that an award of damages, even on an aggregate basis, was subject to two overarching principles as to the award of compensatory damages.[5]  His Honour observed that an award of compensatory damages must be considered in the light of the overriding compensatory principle, and that even where the process of estimating damages is difficult, the Court ‘must do what it can’, this principle equally applying to an assessment of ‘reduction in value’ damages.

Justice Lee found that the Court is not permitted, by s 33Z of the Act, to take an approach of awarding aggregate damages on a per vehicle basis and determining the separate question of distribution at a later stage. Because of this, his Honour was faced with a challenge of how to distribute relief to group members who had possessed the relevant vehicles for only part of the Relevant Period.  His Honour termed these group members as ‘Partial Period Group Members’ and concluded at [432]:

The bottom line is that without knowing the price at which, or the time at which, the Partial Period Group Members bought and sold Relevant Vehicles on the secondary market, one cannot determine on a principled basis how the compensation for the owners of those Relevant Vehicles ought to be assessed or distributed. One must always bear in mind the whole object of any award of damages is to put the claimant in the position the claimant would have been in but for the contravening conduct.

Ultimately, the Partial Period Group Members will be required to undertake an individualised assessment of their loss. For the ‘Entire Period Group Members’, that is, people who possessed the relevant vehicles throughout the entirety of the Relevant Period, the Court awarded aggregate damages under s 33Z(1)(e) of the Act.  The award of aggregate damages for the Entire Period Group Members was calculated on the basis of a 17.5% reduction in value of the average retail price of the particular type of vehicle at the particular time it was purchased.  In circumstances where the group member paid a price lower than the average retail price for their vehicle, the lower of the two prices was said to be the applicable comparator from which the 17.5% reduction in value is to be calculated.[6]  In being satisfied there was a reduction in value of the relevant vehicles of 17.5% resulting from the failure to comply with s 54 of the ACL, Lee J also found that Entire Period Group Members were also entitled to recover the excess GST they paid on that reduction in value, calculated as 10% of the reduction in value.[7]

Regarding the claim for damages under s 33Z(1)(f) of the Act, the Court declined to award aggregate damages on this basis, because his Honour was not satisfied that a reasonably accurate estimate could be made of the total amount owing to group members as required by s 33Z(3).

Conclusion

Williams is the first instance of a Court awarding aggregate damages in a funded representative proceeding, and provides helpful guidance on how the Court will approach such claims, particularly where only part of the claim is suitable for determination on an aggregate basis.  That said, while Justice Lee found in favour of the class on the issue, it is plain that such an assessment will need to be carried out on a case-by-case basis.

About the Authors

Martin del Gallego, Partner

Martin is Chambers & Partners recognised commercial litigator with 15 years’ experience in high stakes, high value litigation. Martin specialises in class action and funded litigation, with expertise across a broad range of sectors including financial services, energy & resources, construction and insolvency.

Matthew Harris, Lawyer

Matthew is a litigation and dispute resolution lawyer at Piper Alderman with a primary focus on corporate and commercial disputes. Matthew is involved in a number of large, complex matters in jurisdictions across Australia.

For queries or comments in relation to this article please contact Kat Gieras, Litigation Group Project Coordinator | T: +61 7 3220 7765 | E:  kgieras@piperalderman.com.au

[1] Williams v Toyota Motor Corporation Australia Limited [2021] FCA 1425.

[2] Federal Court of Australia Act 1976 (Cth) s 33Z(1)(e).

[3] Ibid s 33Z(1)(f).

[4] Ibid s 33Z(3).

[5] Williams [421]-[423].

[6] Williams [446].

[7] Williams [492].